In this example video, there are 23 source Windows® 2008 R2 and 23 Windows® 2016 target servers. A single "Data Migration" job is used as a template for all 23 sites, because all 23 systems have an identical configuration/partitioning. There is no limit to the amount of systems you can migrate with the rollout planning feature. CopyRight2 customers have already successfully migrated environments with 600 source and target systems, a small team of only 2 engineers and a short period of six months with this feature.
CopyRight2 is run on a central console, from where the software is automatically deployed to the remote sites. An Excel sheet in CSV format is used as input to the process, controlling source & target, where the software is run and the point in time when the cut-over should occur.
The rollout is planned to begin slowly with 1 site, then another 1, then 2, followed by 5 and then 14 for the final round. The CopyRight2 GUI allows to centrally monitor the progress of all processes and check for any errors that occurred.
It is possible to connect to the central console from multiple workstations or over RDP to split the workload across multiple team members.